Tillamook Liberty ES ASHRAE Level 2 Energy Audit
Analysis: Facilities energy efficiency evaluation, identification of energy efficiency measures, calibrated energy modeling, cost estimating, and energy cost savings. Department of Energy's Renew America's School and Oregon Department of Education
Review of energy bills usage patterns
Site inspection to evaluate building systems and equipment
Analyze operational data and performance metrics of HVAC, lighting, and other systems
Identify energy-saving opportunities and potential upgrades or retrofits
Estimated costs and savings
EEM 1: Replace Rooftop and Ground Mounted Heat Pumps
EEM 2: Replace existing lighting with LED
EEM 3: Exterior motion sensors
EEM 4: Restroom Occupancy Sensors on Fans
EEM 5: Exterior Door Weather Seals
EEM 6: Additional insulation for building envelope
ASHRAE Normative Forms

Project Team
OWNER: TILLAMOOK SCHOOL DISTRICT
1700 9th Street
Tillamook, OR 97141
Jay Marugg, Transportation / Maintenance Director
P: 503-842-4414
PROJECT MANAGER: COMMUNITY SYSTEMS SOLUTIONS
Public Policy Consultants
Mike Bahr, Grant Manager, Community Systems Solutions
https://communitysystemsolutions.com/
P: 916-827-0016
ASHRAE L2 AUDIT: HELIX ENERGY PARTNERS LLC
113 Main Street, Helix, OR 97835
Michael Lovejoy, PE
P: 541-379-0271
SITE INVESTIGATION: RON ANDERSON CONTROLS INC
38515 Pit Road Philomath, OR 97330
Alan Wright, PhD, PE
P: 541-740-4105