SOU Churchill Hall Commissioning
Renovation: Commissioning services for remodeled 86-year-old Southern Oregon University Churchill Hall. $6.4 million renovation, 32,000 square feet, 3-stories.
Steam/Heating water Converters with Submetering
VAV Air Handling Equipment
Heat Recovery Ventilation
Unit Ventilators
Exhaust Fans
Domestic Hot Water Circulation System
Interface with Central Plant Chilled Water System
Lighting Controls
HVAC fire/smoke alarm interface
Full DDC Building Automation System with advanced Energy Conservation Controls (Night Low Limits, Optimal Start, Occupancy Setback with HVAC and Lighting, Heat Recovery Optimization, Demand Controlled Heating and Cooling Water System, Demand Controlled Ventilation, Electrical Utility Monitoring/Metering)

Project Team
OWNER: SOUTHERN OREGON UNIVERSITY
351 Walker Ave. Ashland, OR 97520
Owner's Rep: Jim McNamara, Drew Gilliland, Keith Beed
P: 541-552-6111
COMMISSIONING: ENVIRONMENTAL & ENGINEERING SERVICES INC (EESI)
687 N.W. 5th Street Corvallis, OR 97330
Michael Lovejoy, PE (Cx, M&P)
Laurel Wong, PE (Cx, E)
P: 541-754-1062
ARCHITECT: ORW ARCHITECTURE
David Wilkerson, AIA, LEED AP
Josh Sizemore
Dave Stevens
Warren Barnhart
2950 East Barnett Road Medford, OR 97504
P: 541-779-5237
MEP ENGINEERING: BALZHISER & HUBBARD ENGINEERS
100 W 13th Avenue Eugene, OR 97401
Mark Penrod, PE
Troy Hanson
Paul Fooks
Tim Ely
Dave Knighton
P: 541-686-8478
STRUCTURAL ENGINEER: ZCS ENGINEERING
10121 SE Sunnyside Rd. Ste 205 Clackamas, OR 97015