New Construction: Commissioning services for 253,000 square foot high school. Medford, Oregon

  • 3 Gas fired condensing boilers

  • 2 Air Cooled variable speed chiller

  • 18 Packaged rooftop units

  • 28 four pipe heat recovery ventilators

  • 19 Split air conditioning systems

  • 68 VAV terminal units

  • 5 radiant floor systems

  • Multiple hydronic pumps

  • Multiple cabinet unit heaters and convectors

  • Multiple exhaust fans

  • Emergency Generator

  • Full DDC Building Automation System

Renovation and New Construction: Commissioning services for 250,000 square foot high school mechanical upgrades in Medford, Oregon.

Project Team

 

OWNER: MEDFORD SCHOOL DISTRICT
2801 Merriman Road Medford, OR 97501
Owner's Rep: Mark Button, Project Manager
Rick Rose, Facilities Manager
P: 541-842-3636

 

COMMISSIONING: ENVIRONMENTAL & ENGINEERING SERVICES INC (EESI)
687 N.W. 5th Street Corvallis, OR 97330
Michael Lovejoy, PE (Cx, M&P)
Alan Wright, PE
Laurel Wong, PE (Cx, E)
Fred Shaub, PE
Lonny Hazelton
Curt Stroben
P: 541-754-1062

 

ARCHITECT: MAHLUM ARCHITECTS, INC.
71 Columbia #400, Seattle, WA 98104
Susan Fore
David Satri
Mark Cork
P: 206-441-4151

 

ARCHITECT: ARCHITECTURAL DESIGN WORKS
1105 Siskiyou Blvd. Box 1346 Ashland, OR 97520
Jac Nickels
Dave Richardson
P: 541-488-0719

 

MEP ENGINEERING: INTERFACE ENGINEERING
708 SW Third Avenue #400 Portland, OR 97204
Brian Butler
David Chesley
Andy Frichtl
P: 503-382-2266

 

CIVIL ENGINEER: DEW ENGINEERING INC.
Medford, OR

 

STRUCTURAL ENGINEER: COUGHLIN PORTER LUNDEEN
Seattle, WA

Helix Energy Partners 로고 BW

+1-541-379-0271

Copyright© 2016 by Helix Energy Partners LLC  헬릭스, 오리건 | 이용약관  | 개인 정보 정책

bottom of page